[ARCHIVED] Long Road Reconstruction Project Update

As this project is approaching completion by the end of June, work planned for the weekend of June 16 and going into the week of June 18 is as follows:

*Saturday, June 16 - pavement stripping will be done on Long Road.  

*Work will continue on the Long Lane/Orchard Road island.

*Monday, June 18 - final paving is scheduled on the side streets at Fox Trail and Long Court.

All work is weather permitting. During these activities, the road will remain open for travel with one-way flagging operations as necessary to assure safety. For more information on the project please visit the project website at LongRoadReconstruction.com or contact John Wannigman, Project Manager at 303-708-6139.

Facebook Twitter Email

Other News in Greenwood Village News

A baby sits in a field with Easter eggs during Greenwood Village egg hunt.

Egg Hunt

Posted on: March 12, 2023
National Prescription Drug Take Back Day

Drug Take Back Day

Posted on: February 27, 2023
GV Cover photo 3-23

March Newsletter

Posted on: March 3, 2023
Road Closure Notice

Road Closure Notice: Cherry Creek Dam Road

Posted on: February 14, 2023
Rollin D. Barnard Equestrian Park

February Newsletter

Posted on: February 2, 2023
Canadian Goose

Avian Flu reported in Greenwood Village

Posted on: January 27, 2023